Wind farm Tera Kora I is operational since 2012 and consists of 5 Vestas V90 3.0MW turbines. In 2017 Topwind was involved in the extension of this wind farm. The extension (5 Vestas V117 3.3MW turbines) is initiated by NuCuraçao Windpark II, a consortium of NuCapital and Aspiravi. After the extension wind farm Tera Kora I & II have a total power of 31.5 MW.
Topwind has been assigned by NuCuraçao Windpark II B.V. to provide the Owner Engineer services. The scope for Topwind includes:
- Inspection at the Vestas factory in Denmark before loading of the main components.
- After shipping of the turbines Topwind was responsible for the quality and Take Over of the turbines and wind farm facilities like SCADA.
- Monitoring and approval of the ‘trial operation’.
- The Owner Engineering is finished with a Take Over inspection to ensure quality and delivery according to the contractual arrangements.